How long does a typical office relocation take?

How long does a typical office relocation take?

What is a realistic timeline from deciding to move to being fully operational?

This depends on the size, scope and the requirements of your project. We suggest you start the process 1 year prior to your anticipated move, which will give you and your broker adequate time to find the right space.  Additionally, we listed some generic timeframes below to help with planning.  Some items can run concurrently and other items below run consecutively.  Having a project manager on board working for your best interest can make sure the schedule and timing is customized for your requirements and that all the elements are coordinated in the most time-effective manner possible.

  • Develop size, cost and timing – 2-6 weeks 
  • Building tours with brokers, test fits, pricing plans lease negotiations, lease signed  – 4-12 weeks 
  • If tenant improvements are required:  
    • Design development – 3-5 weeks 
    • Construction documents – 4-5 weeks 
    • Construction bid process – 3-4 weeks 
    • City permitting process – 6-9 weeks 
  • Bid construction – 2-3 weeks 
  • Construction contracts signed and contractor mobilization – 1-3 weeks 
  • Construction – 12-16 weeks 
  • New furniture tours, bidding, review, make adjustments, place order – 4-16 weeks (typically started before construction) 
  • New furniture lead times – 8-16 weeks 
  • Internet lead times for separate circuits and new service – 1-20 weeks 
  • Bid other services required security, cabling, phones, AV – 2-6 weeks 
  • Final inspection and cleaning prior to move – 1-2 weeks  
  • Move days – 1-3 days, unless multiple phases  